Managing Planning Items
- View and Open Planning Items
- Search and Filter Planning Items
- Edit a Planning Item
- Copy a Planning Item
- Copy a Task
- Rename a Planning Item
- Delete a Planning Item
- Disassociate a Planning Item
- Which Items Can You Disassociate?
- View and Save Planning Information in a File
- Comment on a Planning Item
- Add Attachments to a Planning Item
- Initiate Workflows
- Switch between Planning Mode and Design Mode
View and Open Planning Items
View Planning Items
To view the planning items, on the navigation
bar click
Planning
Plans.
You can view planning items in the following views:
- Table View
-
By default, planning items are displayed in the Table view. All of the information about the planning items is displayed in a tabular format. The total number of items that you added is displayed at the top, based on the criteria that you select in the Advanced Filter pane.
Each planning item is listed in a separate row. Information about the planning items is displayed in the columns. You can hide or display any of the columns. You can also search and filter planning items.
- Calendar View
-
You can view the schedule and duration for the planning items on the calendar, based on the information that you specified for each planning item. In the Calendar view, you can view planning items for the predefined and user-defined time periods that you might specify. You can also see planning items on a Gantt chart.
For more information, see Viewing Planning Items on a Calendar.
Manage Columns in the Table View
You can select and adjust the columns in your
view. Click and select an option:
- Click Manage columns to add or remove columns from your view.
- Click Resize all columns to fit to adjust the column widths, depending on the content in the visible rows.
Open Planning Items
You can open the planning item by using any of the following options:
- From the Table view
-
In the Name column, click a planning item to open it from the default Table view.
- From the Calendar view
-
From the Table view, click
, and then click a planning item to open it in the Calendar view.
- From the Relationships tab
-
From the Relationships tab in a planning item, click an associated planning item at the parent or child level.
- From the Breadcrumb trail
-
When you open several associated planning items, a breadcrumb trail is displayed at the top. You can click a planning item in the breadcrumb trail to open the item.
- From a Workflow
-
On the Details tab of a workflow, the Source field displays the name of the planning item from which the workflow was initiated.
- From a Task
-
If you associated a task with a planning item, click
to open the related planning item. For more information, see Switch between Planning Mode and Design Mode.
View Marketing Hierarchy
You can view the hierarchy of the planning item.
In the Table view for
Planning
Plans, click the planning item to view its details. On the
Relationships tab of the open planning item, you can view the
child planning items, which are arranged in a hierarchical order. For more information, see About Planning Items and Marketing Hierarchies.
Depending on your assigned permissions, you can perform several actions on selected items, such as remove, delete, copy, rename, and export to Microsoft Excel. Use the breadcrumb trail that is available at the top left of the window to return to the previous planning item.
Search and Filter Planning Items
Find Specific Items
On the
Planning
Plans page, by default the Table view and the Calendar view display all of the
items for a selected time period. To find an item by name, by status, or by the user
who
modified the item, enter the relevant keywords in the search box.
To filter items and refine your search, click . You can filter items by Type, Parent
Level, Association, Status,
Approvers, Tags,
Currency, Planned Start Date,
Planned End Date, Date Modified, and
Modified By user name.
For more information, see Search for Items.
In the Advanced Filter pane, if the complete list of items is not displayed, click More. To filter items, in the filter window, select the items or enter relevant keywords in the search box.
Find Items in a Specific Time Period
When you switch from the Table view to the
Calendar view for
Planning
Plans, by default the items that occur in the current month are displayed in the
Month view. You can use the Planned Start
Date and Planned End Date fields to filter items
that occur during the specified time period. You can also use the Date
Modified field to filter items that were modified during the specified time
period.
Click and in the Advanced Filter pane, enter date ranges
for Planned Start Date, Planned End Date,
or Date Modified fields. Depending on the priority that is defined
for these date fields in the calendar definition, the Calendar view
displays the first month of the date range that you specified for that field.
For example, if the priority defined for the Planned Start Date field is 1, the Planned End Date field is 2, and Date Modified field is 3. The Calendar view displays the first month of the date range for the Planned Start Date field.
Work with Enhanced Search Capabilities
The search engine provides an enhanced search experience that enables you to effectively search through long lists and find items quickly and easily.
Perform these actions to search a list of items:
- Enter a
keyword or a group of keywords and click
in the search box or press the ENTER key on your keyboard.
You can also enter one or more search keywords from the file name.
Note: To search for document-type file formats such as .pdf, .doc, and so on, do not enter the text document in the search box. The search results display only asset files that contain the text "document" in the file name or properties. - If you add multiple words in the search box, the search results display the items with item names that are an exact match of the search keywords. The results also display items with item names that contain at least one of the search keywords. This means that the results match all of the search keywords and subsets of the search keywords.
Edit a Planning Item
- On the navigation bar, click
Planning
Plans. - Click a planning item to open it.
- On the Details tab of the open planning item, edit the details.
- Click
to save the changes.
If the currency settings are changed, you need to select a valid currency for the planning item. If a valid currency is not selected, you cannot add any more planning items to the hierarchy. The details of the planning item can be edited.
Copy a Planning Item
There are two ways to copy a planning item:
- On the navigation bar, click
Planning
Plans. - Select the item to be copied.
- Click
and select
.
- Enter a unique planning item number and name for the copy. The default name is item name 1. This action copies only the planning item details, not the items that are associated with the planning item.
In the context of the planning item:
- Click
and select Save as.
- Enter a unique planning item number and name for the copy. The default name is item name 1. This action copies the planning item details and associates the planning item with the parent item. The items that are associated with the planning item are not copied.
Copy a Task
If you associated an existing task or created a task from the Relationships tab of a planning item, you can create a copy of the task.
Complete these actions:
- On the Relationships tab of a planning item, select the task that you want to copy.
- Click
and select
Copy.
The task is copied and listed below the original task on the tasks page.
If a task has a Planning status, the status is retained in the task copy. If the task has any other status, the status of the task copy is reset to Designing.
All of the planning information, as well as the content and design elements from the original task are copied.
Rename a Planning Item
Complete these actions:
- On the navigation bar, click
Planning
Plans. - Select the item to be renamed.
- Click
and select Rename.
- Enter a unique name for the item.
- Click Save.
You cannot rename activities and tasks that are associated with the planning item from the Relationships tab. You can navigate to the Activities or Tasks page and rename the items.
Delete a Planning Item
There are two ways to delete a planning item:
- On the navigation bar, click
Planning
Plans. - Select the items to be deleted.
- Click
.
- Confirm the deletion.
In the context of the open planning item:
- Navigate to the Relationships tab of the planning item.
- Select the items to be deleted.
TipTo delete multiple items simultaneously, select only the child items that share the same parent item. Repeat this step for planning items at each level.
- Click
.
- Confirm the deletion.
Real-time journeys and tasks that are associated with the planning item are not deleted. The journeys and tasks are removed or disassociated from the planning item. Only the selected planning items and the associated planning items are deleted.
Disassociate a Planning Item
You can remove items that are associated with a planning item. Removed items are not deleted from the system, but they are disassociated from the parent planning item.
In the context of the open planning item:
- Navigate to the Relationships tab of the planning item.
- Select the items to be removed.
- Click
.
- Confirm the removal.
Which Items Can You Disassociate?
To simultaneously disassociate multiple items, you must select items that share the same parent planning item.
View and Save Planning Information in a File
Depending on your whether you want to edit, review, share, or save the planning information that you added, you can export planning information to a Microsoft Excel spreadsheet or a read-only PDF file.
Export Planning Information to a Microsoft Excel File
You can export all of the information that you added in a planning item to a Microsoft Excel spreadsheet. You can download the file and save it on your system.
When you download and save information about a planning item in a Microsoft Excel spreadsheet, information about the child planning items that are associated with the selected planning item is also included in the file. A separate worksheet is created for each level of items that are associated with the planning item. The downloaded file contains information about each item.
You can export the custom properties fields and the values that you added in a planning item to a Microsoft Excel spreadsheet. All of the ad hoc properties, connector-driven properties, and table-driven properties and their values that are added from the user interface are included in the exported spreadsheet.
However, if you update the values and import the spreadsheet, the updated values for the table-driven properties are not included. When you save and import the planning item, any table-driven properties values that you might have edited are not updated. Instead, the table-driven properties values are overridden by the existing values.
For connector-driven custom properties, the connector metadata is not exported. Updating the values of connector-driven properties might cause some discrepancies. If you do not want the connector-driven properties to be edited and overwritten, you can mark them as read-only properties. Any values that you might have edited for read-only properties are not updated and saved when you import.
For more information, see About Custom Properties in SAS Customer Intelligence 360: Administration Guide.
On the navigation bar, click
Planning
Plans. You can export the selected planning items in one of the following
ways:
On the page that lists the planning items:
- Select the check boxes for the planning
items that you want to export.
Note: Tasks and real-time journeys are associated with planning items through planning properties. As a result, only those activities and journeys that contain planning properties can be exported.
- Click
and select Export to Excel. You can export only one planning item at a time. All the details that are associated with the planning item are exported to an Excel spreadsheet.
On the Details tab of a planning item:
- Click a planning item to open it.
- On the Details tab,
click
and select Export to Excel.
On the Relationships tab of a planning item:
- Click a planning item to open it.
- On the Relationships tab, select the items that you want to export to a spreadsheet.
- Click
and select Export to Excel.
- When the file download is complete, click Download. You can open and save the downloaded file to your drive.
View Planning Information in a PDF File
You can view the standard properties and custom properties information from a planning item in a PDF viewer. You can download the PDF file and save it to your local drive or a shared network location.
- On the navigation bar, click
Planning
Plans. - Click a planning item to open it.
- In the open planning item, on the
Details tab, click
.
- You can use the options in the PDF file to download a copy of the file and save the downloaded file to your local drive or a shared network location.
Comment on a Planning Item
Post a Comment
- Click
in the upper right corner of an open planning item.
- Enter a comment and click Post.
Manage Comments
You can perform the following actions on an existing comment:
- Click
to edit the comment.
- Click
to delete the comment.
- Respond to the comment.
Add Attachments to a Planning Item
To add an attachment in an open planning item:
- On the Details tab,
click
. The Attachments pane is displayed.
- Click Attach and
select an option from the drop-down menu:
- Select Files to
attach a file. Browse to upload a file that is stored on your system or on a shared
drive. The attached file is added to the list of attachments. Click the file name
to
view or download.
Note: It is recommended that you upload only clean files. Files that you upload are scanned for malicious content such as viruses. Potentially harmful files are not uploaded.
- Select Asset to
attach an asset. Browse to select an asset from the Assets
Selection window in SAS Customer Intelligence
360. Only active assets are available for selection. The
Attachments pane displays the most current version of the
asset that you attached, and also displays the expired status of the asset when the
status has changed after the asset is attached.
To open or download the file, click
and select Open or Download.
To open and view the asset details, click the attachment.
- Select Files to
attach a file. Browse to upload a file that is stored on your system or on a shared
drive. The attached file is added to the list of attachments. Click the file name
to
view or download.
- To delete an attachment, select the check box
next to the file and click
.
The following file types are supported as attachments: .ai, .asf, .avi, .bmp, .dng, .doc, .docx, .eps, .epsf, .flv, .gif, .htm, .html, .xhtml, .img, .indd, .indt, .jpe, .jpeg, .jpg, .mov, .mp2, .mp3, .mp4, .mpeg, .mpg, .pdf, .pict, .png, .ppt, .pptx, .ps, .psd, .sgi, .swf, .tif, .tiff, .txt, .ucf, .wav, .wma, .wmv, .wpd, .wpg, .xls, .xlsx.
Initiate Workflows
You can initiate a workflow from the Workflows tab of an item to manage work assignments for the item and track progress. Within a workflow, a workflow initiator can assign tasks to contributors (users and groups) and activate the workflow.
In an active workflow, a workflow initiator can view and update the status of the workflow, post comments, share resources, attach files, and track the progress of the assigned workflow tasks.
Workflow contributors can view and update the status of workflow tasks, share resources, post comments, and attach files.
For more information, see Create a Generic Workflow.
Switch between Planning Mode and Design Mode
When a task or a real-time journey is associated with a planning item, you can work on the task or journey in the Planning mode or in the Design mode.
Tasks and real-time journeys are created in the Design mode. In the Design mode, you can specify the information that you need to create and deliver content to your customers through the tasks and journeys.
Tasks and real-time journey are associated with a planning item to enable you to group all of the information that is relevant to a marketing goal. In the Planning mode, you can specify the information that you need to plan and execute the tasks and journeys.
In a task or a real-time journey that is associated with a planning item, you can easily switch between the Planning mode and Design mode.
- To edit a real-time journey, open the
associated journey from the planning item. On the Details tab
click
to switch to the design mode. Click
to return to the planning mode.
- To edit a task, open the associated task from
the planning item. On the Details tab, click
to switch to the design mode. You can edit the task and click
to return to the planning mode.