The CLP Procedure

Example 4.10 Resource-Constrained Scheduling Problem with Nonstandard Temporal Constraints

This example illustrates the use of the cumulative constraint to solve a resource-constrained project scheduling problem that has nonstandard temporal constraints.

For more information about this example, see the same example in SAS/OR User's Guide: Constraint Programming, which illustrates the capabilities of the scheduling solver.

Output 4.10.1: The Bridge Problem

The Bridge Problem


The project consists of 44 tasks and a set of constraints that relate these tasks. Table 11 displays the activity information, standard precedence constraints, and resource constraints. The sharing of a unary resource by multiple activities results in the resource constraints being disjunctive in nature.

Table 11: Data for Bridge Construction

Activity Description Duration Predecessors Resource
  pa Beginning of project 0   
  a1 Excavation (abutment 1) 4    pa Excavator
  a2 Excavation (pillar 1) 2    pa Excavator
  a3 Excavation (pillar 2) 2    pa Excavator
  a4 Excavation (pillar 3) 2    pa Excavator
  a5 Excavation (pillar 4) 2    pa Excavator
  a6 Excavation (abutment 2) 5    pa Excavator
  p1 Foundation piles 2 20    a3 Pile driver
  p2 Foundation piles 3 13    a4 Pile driver
  ue Erection of temporary housing 10    pa
  s1 Formwork (abutment 1) 8    a1 Carpentry
  s2 Formwork (pillar 1) 4    a2 Carpentry
  s3 Formwork (pillar 2) 4    p1 Carpentry
  s4 Formwork (pillar 3) 4    p2 Carpentry
  s5 Formwork (pillar 4) 4    a5 Carpentry
  s6 Formwork (abutment 2) 10    a6 Carpentry
  b1 Concrete foundation (abutment 1) 1    s1 Concrete mixer
  b2 Concrete foundation (pillar 1) 1    s2 Concrete mixer
  b3 Concrete foundation (pillar 2) 1    s3 Concrete mixer
  b4 Concrete foundation (pillar 3) 1    s4 Concrete mixer
  b5 Concrete foundation (pillar 4) 1    s5 Concrete mixer
  b6 Concrete foundation (abutment 2) 1    s6 Concrete mixer
  ab1 Concrete setting time (abutment 1) 1    b1
  ab2 Concrete setting time (pillar 1) 1    b2
  ab3 Concrete setting time (pillar 2) 1    b3
  ab4 Concrete setting time (pillar 3) 1    b4
  ab5 Concrete setting time (pillar 4) 1    b5
  ab6 Concrete setting time (abutment 2) 1    b6
  m1 Masonry work (abutment 1) 16    ab1 Bricklaying
  m2 Masonry work (pillar 1) 8    ab2 Bricklaying
  m3 Masonry work (pillar 2) 8    ab3 Bricklaying
  m4 Masonry work (pillar 3) 8    ab4 Bricklaying
  m5 Masonry work (pillar 4) 8    ab5 Bricklaying
  m6 Masonry work (abutment 2) 20    ab6 Bricklaying
  l Delivery of the preformed bearers 2    Crane
  t1 Positioning (preformed bearer 1) 12    m1, m2, l Crane
  t2 Positioning (preformed bearer 2) 12    m2, m3, l Crane
  t3 Positioning (preformed bearer 3) 12    m3, m4, l Crane
  t4 Positioning (preformed bearer 4) 12    m4, m5, l Crane
  t5 Positioning (preformed bearer 5) 12    m5, m6, l Crane
  ua Removal of the temporary housing 10   
  v1 Filling 1 15    t1 Caterpillar
  v2 Filling 2 10    t5 Caterpillar
  pe End of project 0    t2, t3, t4, v1, v2, ua


The following constraints are added to the standard precedence constraints:

  • The time between the completion of a particular formwork and the completion of its corresponding concrete foundation is at most four days:

    f left-parenthesis normal s i right-parenthesis greater-than-or-equal-to f left-parenthesis normal b i right-parenthesis minus 4 comma i equals 1 comma ellipsis comma 6
  • There are at most three days between the end of a particular excavation (or foundation piles) and the beginning of the corresponding formwork:

    f left-parenthesis normal a i right-parenthesis greater-than-or-equal-to s left-parenthesis normal s i right-parenthesis minus 3 comma i equals 1 comma 2 comma 5 comma 6

    and

    f left-parenthesis normal p Baseline 1 right-parenthesis greater-than-or-equal-to s left-parenthesis normal s Baseline 3 right-parenthesis minus 3
    f left-parenthesis normal p Baseline 2 right-parenthesis greater-than-or-equal-to s left-parenthesis normal s Baseline 4 right-parenthesis minus 3
  • The formworks must start at least six days after the beginning of the erection of the temporary housing:

    s left-parenthesis normal s i right-parenthesis greater-than-or-equal-to s left-parenthesis normal u normal e right-parenthesis plus 6 comma i equals 1 comma ellipsis comma 6
  • The removal of the temporary housing can start at most two days before the end of the last masonry work:

    s left-parenthesis normal u normal a right-parenthesis greater-than-or-equal-to f left-parenthesis normal m i right-parenthesis minus 2 comma i equals 1 comma ellipsis comma 6
  • The delivery of the preformed bearers occurs exactly 30 days after the beginning of the project:

    s left-parenthesis normal l right-parenthesis equals s left-parenthesis normal p normal a right-parenthesis plus 30

For convenience, the activity name is used to represent the start time variable of the activity. Each temporal constraint is represented by a linear constraint in the Constraint data table. An additional observation is added to the Constraint data table to define the objective of minimizing the makespan, which in this case is the milestone p e, indicating the end of the project. The CLP procedure is invoked with the WDEG variable selection strategy along with seven cumulative constraints, one corresponding to each of the resources: Excavator, Pile Driver, Carpentry, Concrete Mixer, Bricklaying, Crane, and Caterpillar.



proc clp condata=mylib.condata varselect=wdeg out=mylib.out usecondatavars=1;
   obj lb=0 ub=2000;
   cumulative (start=( m1-m6 ) dur=( 16 8 8 8 8 20 ))
              (start=( s1-s6 ) dur=( 8 4 4 4 4 10 ))
              (start=( v1 v2 ) dur=( 15 10 ))
              (start=( b1-b6 ) dur=( 1 1 1 1 1 1))
              (start=( l t1-t5 ) dur=( 2 12 12 12 12 12 ))
              (start=( a1-a6 ) dur=( 4 2 2 2 2 5))
              (start=( p1 p2 ) dur=( 20 13 ));
run;

The solution summary shown in Output 4.10.2 reports an optimal objective value of 104 days.

Output 4.10.2: Bridge Construction Solution Summary

The CLP Procedure

Solution Summary
Solution StatusOptimal
Variable SelectionWDEG
Value SelectionMIN
  
Objective SenseMinimization
Objective Value104
  
Solutions Found1
Solution Time19.1


The solution data table shown in Output 4.10.3 displays the corresponding start times for all the tasks.

Output 4.10.3: Bridge Construction Task Start Times

s1a1s2a2p1a3p2a4s5a5s6a6m1ab1m2ab2m3ab3m4ab4m5ab5m6ab6b1b2b3s3b4s4b5b6t1lt2t3t4t5uapauev1pev2
14862202241062618362312112827524120156037221026224036143652303664928078006410492


A Gantt chart of the resulting schedule, zoned by resource, is shown in Output 4.10.4.

Output 4.10.4: Bridge Construction Schedule

Bridge Construction Schedule