The CLP Procedure
Example 4.10 Resource-Constrained Scheduling Problem with Nonstandard Temporal Constraints
This example illustrates the use of the cumulative constraint to solve a resource-constrained project scheduling problem that has nonstandard temporal constraints.
For more information about this example, see the same example in SAS/OR User's Guide: Constraint Programming, which illustrates the capabilities of the scheduling solver.
Output 4.10.1: The Bridge Problem

The project consists of 44 tasks and a set of constraints that relate these tasks. Table 11 displays the activity information, standard precedence constraints, and resource constraints. The sharing of a unary resource by multiple activities results in the resource constraints being disjunctive in nature.
Table 11: Data for Bridge Construction
| Activity | Description | Duration | Predecessors | Resource |
|---|---|---|---|---|
| pa | Beginning of project | 0 | ||
| a1 | Excavation (abutment 1) | 4 | pa | Excavator |
| a2 | Excavation (pillar 1) | 2 | pa | Excavator |
| a3 | Excavation (pillar 2) | 2 | pa | Excavator |
| a4 | Excavation (pillar 3) | 2 | pa | Excavator |
| a5 | Excavation (pillar 4) | 2 | pa | Excavator |
| a6 | Excavation (abutment 2) | 5 | pa | Excavator |
| p1 | Foundation piles 2 | 20 | a3 | Pile driver |
| p2 | Foundation piles 3 | 13 | a4 | Pile driver |
| ue | Erection of temporary housing | 10 | pa | |
| s1 | Formwork (abutment 1) | 8 | a1 | Carpentry |
| s2 | Formwork (pillar 1) | 4 | a2 | Carpentry |
| s3 | Formwork (pillar 2) | 4 | p1 | Carpentry |
| s4 | Formwork (pillar 3) | 4 | p2 | Carpentry |
| s5 | Formwork (pillar 4) | 4 | a5 | Carpentry |
| s6 | Formwork (abutment 2) | 10 | a6 | Carpentry |
| b1 | Concrete foundation (abutment 1) | 1 | s1 | Concrete mixer |
| b2 | Concrete foundation (pillar 1) | 1 | s2 | Concrete mixer |
| b3 | Concrete foundation (pillar 2) | 1 | s3 | Concrete mixer |
| b4 | Concrete foundation (pillar 3) | 1 | s4 | Concrete mixer |
| b5 | Concrete foundation (pillar 4) | 1 | s5 | Concrete mixer |
| b6 | Concrete foundation (abutment 2) | 1 | s6 | Concrete mixer |
| ab1 | Concrete setting time (abutment 1) | 1 | b1 | |
| ab2 | Concrete setting time (pillar 1) | 1 | b2 | |
| ab3 | Concrete setting time (pillar 2) | 1 | b3 | |
| ab4 | Concrete setting time (pillar 3) | 1 | b4 | |
| ab5 | Concrete setting time (pillar 4) | 1 | b5 | |
| ab6 | Concrete setting time (abutment 2) | 1 | b6 | |
| m1 | Masonry work (abutment 1) | 16 | ab1 | Bricklaying |
| m2 | Masonry work (pillar 1) | 8 | ab2 | Bricklaying |
| m3 | Masonry work (pillar 2) | 8 | ab3 | Bricklaying |
| m4 | Masonry work (pillar 3) | 8 | ab4 | Bricklaying |
| m5 | Masonry work (pillar 4) | 8 | ab5 | Bricklaying |
| m6 | Masonry work (abutment 2) | 20 | ab6 | Bricklaying |
| l | Delivery of the preformed bearers | 2 | Crane | |
| t1 | Positioning (preformed bearer 1) | 12 | m1, m2, l | Crane |
| t2 | Positioning (preformed bearer 2) | 12 | m2, m3, l | Crane |
| t3 | Positioning (preformed bearer 3) | 12 | m3, m4, l | Crane |
| t4 | Positioning (preformed bearer 4) | 12 | m4, m5, l | Crane |
| t5 | Positioning (preformed bearer 5) | 12 | m5, m6, l | Crane |
| ua | Removal of the temporary housing | 10 | ||
| v1 | Filling 1 | 15 | t1 | Caterpillar |
| v2 | Filling 2 | 10 | t5 | Caterpillar |
| pe | End of project | 0 | t2, t3, t4, v1, v2, ua |
The following constraints are added to the standard precedence constraints:
-
The time between the completion of a particular formwork and the completion of its corresponding concrete foundation is at most four days:
-
There are at most three days between the end of a particular excavation (or foundation piles) and the beginning of the corresponding formwork:
and
-
The formworks must start at least six days after the beginning of the erection of the temporary housing:
-
The removal of the temporary housing can start at most two days before the end of the last masonry work:
-
The delivery of the preformed bearers occurs exactly 30 days after the beginning of the project:
For convenience, the activity name is used to represent the start time variable of the activity. Each temporal constraint is represented by a linear constraint in the Constraint data table. An additional observation is added to the Constraint data table to define the objective of minimizing the makespan, which in this case is the milestone , indicating the end of the project. The CLP procedure is invoked with the WDEG variable selection strategy along with seven cumulative constraints, one corresponding to each of the resources: Excavator, Pile Driver, Carpentry, Concrete Mixer, Bricklaying, Crane, and Caterpillar.
proc clp condata=mylib.condata varselect=wdeg out=mylib.out usecondatavars=1;
obj lb=0 ub=2000;
cumulative (start=( m1-m6 ) dur=( 16 8 8 8 8 20 ))
(start=( s1-s6 ) dur=( 8 4 4 4 4 10 ))
(start=( v1 v2 ) dur=( 15 10 ))
(start=( b1-b6 ) dur=( 1 1 1 1 1 1))
(start=( l t1-t5 ) dur=( 2 12 12 12 12 12 ))
(start=( a1-a6 ) dur=( 4 2 2 2 2 5))
(start=( p1 p2 ) dur=( 20 13 ));
run;
The solution summary shown in Output 4.10.2 reports an optimal objective value of 104 days.
Output 4.10.2: Bridge Construction Solution Summary
| Solution Summary | |
|---|---|
| Solution Status | Optimal |
| Variable Selection | WDEG |
| Value Selection | MIN |
| Objective Sense | Minimization |
| Objective Value | 104 |
| Solutions Found | 1 |
| Solution Time | 19.1 |
The solution data table shown in Output 4.10.3 displays the corresponding start times for all the tasks.
Output 4.10.3: Bridge Construction Task Start Times
| s1 | a1 | s2 | a2 | p1 | a3 | p2 | a4 | s5 | a5 | s6 | a6 | m1 | ab1 | m2 | ab2 | m3 | ab3 | m4 | ab4 | m5 | ab5 | m6 | ab6 | b1 | b2 | b3 | s3 | b4 | s4 | b5 | b6 | t1 | l | t2 | t3 | t4 | t5 | ua | pa | ue | v1 | pe | v2 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 14 | 8 | 6 | 2 | 2 | 0 | 22 | 4 | 10 | 6 | 26 | 18 | 36 | 23 | 12 | 11 | 28 | 27 | 52 | 41 | 20 | 15 | 60 | 37 | 22 | 10 | 26 | 22 | 40 | 36 | 14 | 36 | 52 | 30 | 36 | 64 | 92 | 80 | 78 | 0 | 0 | 64 | 104 | 92 |
A Gantt chart of the resulting schedule, zoned by resource, is shown in Output 4.10.4.
Output 4.10.4: Bridge Construction Schedule